中文原创av,日韩黄色在线视频,欧美日韩操,亚洲精品国产精品国自产网站按摩,欧美日韩国产一区二区在线观看,男人久久久,亚洲精品久久网白云av

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During project executing, your project team member delivers a project deliverable to the buyer. However, the buyer refuses the deliverable, stating that it does not meet the requirement on page 300 of the technical specifications. You review the document and find that you agree. What is the BEST thing to do?
A、Explain that the contract is wrong and should be changed.
B、Issue a change order.
C、Review the requirements and meet with the responsible team member to review the WBS dictionary.
D、Call a meeting of the team to review the requirement on page 300.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容