試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

Project manager is managing a five months’ project with cost-reimbursable contract and has a total of 500 tasks, of which 100 are completed after two months. All tasks cost and duration are equally dispersed over the months. The following diagram expresses the performance.How many more months would the project manager expect to finish the project?

A、Four months

B、Five months

C、Eight months

D、Ten months