中文原创av,日韩黄色在线视频,欧美日韩操,亚洲精品国产精品国自产网站按摩,欧美日韩国产一区二区在线观看,男人久久久,亚洲精品久久网白云av

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A core project team performed the initial phase of the project stakeholder analysis. The results of the analysis show that a few stakeholders on the project has some negative effect. What should the project manager do next ?
A、Update the project risk log with the project and analysis results.
B、Engage the stakeholders to understand their project expectations.
C、Develop a communication management plan based on the analysis.
D、Develop a plan to manage stakeholder engagement levels.


相關(guān)試題

推薦文章