A project in the final states of the execution phase has a schedule performance index of 0.9. The project team member submits a change request that impacts the project schedule and cost factors. What should the project manager do next ?
A、Inform the project team.
B、Update the change log.
C、Re-project basis.
D、Inform stakeholders.