試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The project is the middle of a long-term project when a major error is discovered by the develop team. This error can be fixed by implementing a large change to the scope of the project. This change could influence both time and budget plans. What should the project manager do first?
A、Analyze the change request and present it to the change control board.
B、 Implement the change request and inform the stakeholders afterwards.
C、 Implement the change request and present it to the change control board afterwards.
D、 Analyze the change request and present it to the steering committee.