試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At a project status team meeting, one team member disagrees with another team member regarding a corrective action. The debate escalates and they are soon both adamantly, Other team members are not participating. The project manager directs the team on the corrective action to use.  What conflict resolution technique did the project manager use ?
A、Compromising
B、Forcing
C、Withdrawing
D、Smoothing