試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the execution phase, marketing informs the sponsor that focus groups give the product mixed reviews and a minor change is required 、 The sponsor instructs the project manager to incorporate the change, because it will not change the scope or budget. What should the project manager do next ?
A、Document the requested change.
B、 Assign responsibility for implementing the change.
C、 Communicate the change to the affected parties.
D、 Convene the team to evaluate the impact of the change.