中文原创av,日韩黄色在线视频,欧美日韩操,亚洲精品国产精品国自产网站按摩,欧美日韩国产一区二区在线观看,男人久久久,亚洲精品久久网白云av

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 《信息系統(tǒng)項目管理師3年真題透解與全真模擬》模擬試題一
考試中心《《信息系統(tǒng)項目管理師3年真題透解與全真模擬》模擬試題一》在線考試
試卷年份2013年上半年
試題題型【單選題】
試題內(nèi)容

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )
A. change the scope baseline
B. call a meeting of the configuration control board
C. assign change tasks to project members
D. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容