項目經(jīng)理正在管理一個項目,向眾多機(jī)構(gòu)交付新的報告產(chǎn)品,該項目必須遵守立法變化,若要確保成功交付,項目

A project manager is leading a project to deliver new reporting product to a large number of agencies. This project must adhere to legislative changes. What should the project manager do to ensure successful delivery?

項目經(jīng)理正在管理一個項目,向眾多機(jī)構(gòu)交付新的報告產(chǎn)品,該項目必須遵守立法變化,若要確保成功交付,項目經(jīng)理應(yīng)該怎么做?

A.Brainstorm with the team to devise a risk  mitigation plans與團(tuán)隊一起頭腦風(fēng)暴,制定風(fēng)險減輕計劃

B.Identify and document the project’s risks and necessary success criteria識別并記錄項目的風(fēng)險和必要的成功標(biāo)準(zhǔn)

C.Meet with stakeholders to communicate the schedule, budget and cost impacts in the event與相關(guān)方開會,溝通項目延期對進(jìn)度計劃、預(yù)算和成本的影響

D.Ask a vendor to submit a plan for system support, training and disaster recovery要求供應(yīng)商提交一份關(guān)于系統(tǒng)支持、培訓(xùn)和災(zāi)難復(fù)原的計劃

信管網(wǎng)參考答案:B

信管網(wǎng)解析:

B是參考答案。立法的變化是項目的主要風(fēng)險,應(yīng)該提前識別項目風(fēng)險,明確項目成功標(biāo)準(zhǔn)有助于確保項目成功。參考章節(jié)1.2.6.4

信管網(wǎng)訂閱號

信管網(wǎng)視頻號

信管網(wǎng)抖音號

溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。

信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。

相關(guān)內(nèi)容

發(fā)表評論  查看完整評論  

報考條件查詢

推薦文章

精選

課程

提問

評論

收藏